December Seven Hills Community Update

Posted on
Exterior brick and siding installation on north side.

MARKETING UPDATE:

  • Model Unit finished in November. Open for prospective residents and their families to tour on weekends.
  • Leasing update:
    • 8 total reservations
    • 2 signed leases for March 1, 2020 move-in
  • Marketing update:
    • Ads running in The Village, to include our “Model Open”.
    • New signage ordered for building site to include “Model Open and Now Leasing”.
    • Educational Series – ‘Downsizing Seminar’ scheduled for prospects/public for January 22.
    • Google Ad words and social media advertising driving website traffic.

CONSTRUCTION UPDATE:
Current Status:

  • Framing and roof is 100% complete.
  • Permanent Power has been connected to the building.
  • East Half:
    • Mechanical is 80% complete with Magic-Paks being set into residential units.
    • Electrical is 75% complete.
    • Cabinetry is 95% complete.
    • Punch list work will begin in January.
  • West Half:
    • Mechanical is 50% complete.  Installation of sleeves for residential unit Magic-Pak HVAC in progress and final rough-ins at main common areas on 1st floor.
    • Electrical is 65% complete.
    • Cabinetry and finish work continues on 3rd and 4th floors.
  • Building Exterior:
    • Brick masonry work is 50% complete.
    • Exterior siding is 80% complete.