MARKETING UPDATE:
- Model Unit finished in November. Open for prospective residents and their families to tour on weekends.
- Leasing update:
- 8 total reservations
- 2 signed leases for March 1, 2020 move-in
- Marketing update:
- Ads running in The Village, to include our “Model Open”.
- New signage ordered for building site to include “Model Open and Now Leasing”.
- Educational Series – ‘Downsizing Seminar’ scheduled for prospects/public for January 22.
- Google Ad words and social media advertising driving website traffic.
CONSTRUCTION UPDATE:
Current Status:
- Framing and roof is 100% complete.
- Permanent Power has been connected to the building.
- East Half:
- Mechanical is 80% complete with Magic-Paks being set into residential units.
- Electrical is 75% complete.
- Cabinetry is 95% complete.
- Punch list work will begin in January.
- West Half:
- Mechanical is 50% complete. Installation of sleeves for residential unit Magic-Pak HVAC in progress and final rough-ins at main common areas on 1st floor.
- Electrical is 65% complete.
- Cabinetry and finish work continues on 3rd and 4th floors.
- Building Exterior:
- Brick masonry work is 50% complete.
- Exterior siding is 80% complete.