- Advertising in area newspapers is now reflecting our move-in date which is coming soon, March 1, 2020.
- Social Media campaign with specific targeting inside a 15 mile radius, started October 22. This campaign includes Facebook, Instagram, & Google management.
- Competitive search engine advertising is projected to start on November 11.
- Model apartment for prospective residents is planned to be completed for tours prior to Thanksgiving.
- Executive Director to start mid-November, who along with the Sales Coordinator, will be meeting with residents and families from our qualified prospect list to get commitments.
CONSTRUCTION UPDATE:
Current Status:
- Framing is at 98% complete.
- Plumbing is 90% complete on east half and 20% complete on west half.
- East: Finishing water lines on 3rd and 4th floors. 1st and 2nd floor east side framing punch getting ready for rough-in’s.
- West: Core drilling 1st and 2nd floors. Residential units and common area plumbing rough-ins on 3rd and 4th floors.
- HVAC is 45% complete. Installation of sleeves for unit Magic Pak HVAC in progress. HVAC shafts are being installed.
- Electric is 50% complete.
- Interior Finishes: Insulation and sheetrock work is ongoing. Unit cabinets, doors and trim have been delivered.
Building Exterior:
- Brick masonry work is 20% complete.
- Exterior siding started wk of October 21.
Next two weeks:
- Roofing started week October 21 and expected to be complete by November 4.
- Alley Bituminous work to begin week of November 4.
- Gypcrete being poured on 2nd floor west side.
- Begin installation of finishes on 4th floor east side; painting, flooring and cabinets.