January Seven Hills Community Update

Posted on

CONSTRUCTION UPDATE:

Current Status:

  • Beginning January 4, construction has been the installation of precast foundation walls and plank.
  • All precast work will be completed by February 8.
  • The construction site was shut down for a few days due to the extreme cold weather conditions.

Next Two Weeks:

  • Framing layout will commence the week of February 4.

Follow this link to visit our live construction site camera:  It is currently inoperable due to the extreme cold temperatures, but we are working on a fix.  Hopefully soon you will be able to view the construction work live.
https://www.senserasystems.com/public/project/CBSconstructionsevenhillsseniorliving